INITIATION

Objectives

  • Establish Goals and Objectives
  • Launch Project Website
  • Establish a Planning Advisory Committee (PAC)

Meetings

  • PAC Meeting #1
  • Public Information Workshop #1
DTO plane white down

PHASE ONE

(TBD)

Objectives

  • Inventory of Existing Conditions
  • Environmental Inventory
  • Aviation Forecasts
  • Draft Phase One Working Papers

Meetings

  • PAC Meeting #2
  • Public Information Workshop #2
DTO plane white down

PHASE TWO

(TBD)

Objectives

  • Facility Requirements
  • Airside/Landside Alternatives
  • Sustainability Management Plan (Throughout)
  • Draft Phase Two Working Papers

Meetings

  • PAC Meeting #3
  • Public Information Workshop #3
DTO plane white down

PHASE THREE

(TBD)

Objectives

  • Recommended Development Concept
  • Environmental Overview
  • Capital Improvement Program
  • Airport Layout Plan Drawings
  • Economic Benefit Analysis
  • Draft Phase Three Working Papers

Meetings

  • PAC Meeting #4
  • Public Information Workshop #4
DTO plane white down

FINALIZATION

(TBD)

Objectives

  • Draft Final Master Plan Report
  • Deliver Digital and Printed Copies of Finalized Report

Approvals

  • ALP Approval by Federal Aviation Administration (FAA)
  • Local Approval of ALP